In the table below are details of recent applications received in the Building Department along with their status through permit issuance. The table is updated on a weekly basis. Applications for which a permit has been issued remain in the table for up to one month, regardless of actual progress on the job site. This means that more issued permits and ongoing projects exist than are listed in this table and that some finalized or closed permits may still be listed here for some time after the job is finished. 

The Building Clerk proactively keeps in touch with contractors regarding the status of their permits throughout the process of approval, issuance and closure. Contractors are not required to rely on this table to know the status of their applications. Should you have any questions or need more information about a permit included in the table or a project not listed here, please contact Teresa Brown at buildingclerk [at] townoforchid.com (buildingclerk[at]townoforchid[dot]com) or by telephone at (772) 581-2770 at ext. 3. You may also request copies of documents pertaining to current or past permits.

Below the table are provided further details about the status types. 

Building Permit Application Status
Permit Number Project Address Contractor Scope of Work Application Status Issue Date
2026-105 340 Westwind Court Della Porta Construction Addition and Reno Permit Issued 6/10/2026
2026-110 537 White Pelican Circle Temp Control AC Replacement Permit Issued 6/1/2026
2026-111 606 Heron Point Court Temp Control AC Replacement Permit Issued 6/1/2026
2026-112 151 Beachside Drive Vero Glass & Mirror Door Replacement Permit Issued 6/3/2026
2026-113 385 Indies Drive Molinari Pools Pool Reno Permit Issued 6/3/2026
2026-114 30 Beachside Drive 101 Tozzolo Brothers Renovation Permit Issued 6/11/2026
2026-115 512 White Pelican Circle TH Whitfield Construction Demolition Permit Issued 6/8/2026
2026-116 151 Beachside Drive Shoreline Shutters Shutters Permit Issued 6/15/2026
2026-117 411 Indies Drive Shoreline Shutters Shutters Permit Issued 6/17/2026
2026-118 100 Beachside Drive 303 Kevin Lovely Plumbing Plumbing Permit Issued 6/11/2026
2026-119 150 Seaspray Lane Barker AC AC Replacement Permit Issued 6/15/2026
2026-120 418 Indies Drive Complete Electric Generator Application Incomplete  
2026-121 500 White Pelican Circle Barker AC AC Replacement Permit Issued 6/15/2026
2026-122 201 Beachside Drive Barker AC AC Replacement Permit Issued 6/15/2026
2026-123 201 Beachside Drive  Barker AC AC Replacement Review in Progress 6/15/2026
2026-124 541 White Pelican Circle Ed Crocker Construction Impervious Surface Permit Issued 6/29/2026
2026-125 1 Beachside Drive Pye Barker Fire Sprinklers Application Incomplete  
2026-126 171 Seaspray Lane Temp Control AC Replacement Permit Issued 6/25/2026
2026-127 80 Beachside Drive 101 Samberg Construction Plumbing Review In Progress  
2026-128 800 Pembroke Court Clear Choice Windows Window Door Replacement Permit Issued 7/1/2026
2026-129 538 White Pelican Circle Florida Shutters Shutters Permit Issued 7/2/2026
2026-130 41 Caribe Way Clear Choice Windows Window Door Replacement Permit Issued 7/2/2026
2026-131 171 Seaspray Lane All Star Plumbing Plumbing Permit Issued 7/2/2026
2026-132 943 Orchid Point Way Shoreline Shutters Shutters Review In Progress  
2026-133 916 Orchid Point Way Dirtywork Environmental Gas Review In Progress  
2026-134 607 Heron Point Court Grimes AC AC Replacement Review In Progress  
  • Review In Progress: An application has been received by the Town and is under review by the Town's Building Official and/or Engineer.
  • Application Incomplete: An application has been received by the Town, but it is incomplete. An application may be incomplete upon initial submittal because a contractor is providing the necessary documentation piecemeal, or may be found to be missing information or require correction during the review process. When an application's status is "Application Incomplete", the contractor has been notified of what is needed for the application to progress through approval and permit issuance.
  • Permit Issued: The permit application has been approved and the contractor has been notified of its issuance.