Expenditures are capitalized when the cost of a good or construction project exceeds $1,000 and has an expected life of at least one year. This is a very low capitalization threshold, but suits the Town’s small-scale nature. Capital assets tracked as fixed assets are subject to straight-line depreciation based on expected useful life. Assets not yet placed in service (i.e. in inventory) are not depreciated.
Generally, these expected useful life spans apply:
- Streetlight Heads & Poles – 20 years
- Furniture & Fixtures – 10-20 years
- Machinery & Equipment – 5-20 years
- Building Improvements – 15 years
- Infrastructure Improvements (including dune repair projects) – 5 years
Dune repairs are the highest value listings on the schedule and are depreciated over a short period of time. This combination causes the greatest fluctuations year over year.
The following table summarizes changes in the Town's net capital assets. For fiscal years prior to the current year, the amounts shown are audited figures. Amounts for the current and next fiscal year are estimates. The estimate for next fiscal year assumes no capital asset additions or dispositions and therefore reflects only projected depreciation and amortization where applicable. Actual results are expected to differ as capital asset activity occurs during the year; after all, the budget for Fiscal Year 2026-2027 includes amounts for possible capital expenditures.
| Net Capital Assets | FY 2022 Actual | FY 2023 Actual | FY 2024 Actual | FY 2025 Actual | FY 2026 Estimate | FY 2027 Estimate |
|---|---|---|---|---|---|---|
| Buildings incl. improvements | 53,936 | 49,035 | 40,021 | 35,771 | 31,521 | 27,271 |
| Streetlights in Inventory | 1,552 | 7,726 | 10,447 | 9,197 | 11,629 | 11,629 |
| Streetlights in Service | 95,984 | 88,362 | 83,363 | 85,635 | 81,162 | 71,053 |
| Furniture & Fixtures | 1,844 | 1,137 | 8,117 | 6,855 | 5,592 | 4,330 |
| Machinery & Equipment | 4,510 | 3,281 | 7,013 | 5,153 | 3,294 | 1,637 |
| Construction in Progress | 0 | 0 | 0 | 8,500 | 0 | 0 |
| Infrastructure (Dune Repairs) | 0 | 493,436 | 379,566 | 265,696 | 624,819 | 401,797 |
| Right-to-Use Lease | 0 | 0 | 290,203 | 270,553 | 250,903 | 231,253 |
| Total | 157,826 | 642,977 | 818,730 | 687,360 | 1,008,920 | 748,970 |
The Town’s Inventory Management Policy requires a comprehensive review of the Town’s streetlights and its furniture and equipment on three-year cycles respectively. For the latter, this review includes items that may not be on the Town’s fixed asset list. When circumstances may cause an asset to carry a greater value on the books than its fair value, the Town reviews its assets for impairment. This is particularly applicable to dune repair projects.
Five-Year Capital Expenditure Plan
The Town’s Five-Year Capital Expenditure Plan, adopted annually by ordinance, includes $0 for all required categories. This is due to the Town’s limited area of responsibility, which excludes most infrastructure within the community, which instead fall within the purview of the Orchid Island Golf & Beach Club or Community Association, or Indian River County. As explained, the Town Council recognizes a role for the Town in coastal management, but because those projects are done on an ad hoc basis under emergency conditions, they are not earmarked in the long-term plan. Furthermore, streetlights are purchased on an ad hoc basis to maintain a small inventory as needed, and such purchases are not mapped out in the schedule.
Basin Management Action Plan
Relatively recently, the Town became a full stakeholder in the Central Indian River Lagoon Basin Management Action Plan (BMAP), which aims to reduce annual nutrient loading of nitrogen and phosphorus. The Town has been assigned reduction objectives with certain milestones upcoming in 2030 and 2035. It is important to note that the Town unexpectedly lost its low-priority stakeholder designation in mid-2025 and is in a position of having to catch up to neighboring stakeholders who had to actively pursue nutrient reduction objectives for over a decade. In the table below are provided the current reduction targets by milestone (subject to change with updates to the underlying Spatial Watershed Iterative Loading model).
| Total Milestones | Overall Reduction Requirement | Entity Requirement Nitrogen (lbs./yr) | Entity Requirement Phosphorus (lbs./yr) |
|---|---|---|---|
| 2025 Milestone | 35% | 479 | 87 |
| 2030 Milestone | 70% | 958 | 174 |
| 2035 Milestone | 100% | 1,368 | 248 |
The Town did not meet the 2025 milestone targets, because of its delayed inclusion as a full stakeholder in that same year, which meant that projects undertaken by the community in the first decade of the program that may have positively impacted the Town’s nutrient loads, or that could have been designed to, were not creditable.
The Town recognizes that its ability to achieve assigned total nitrogen and total phosphorus reductions is constrained by its size, nearly built-out condition, limited municipal staffing and resources, and complete lack of Town-owned land or infrastructure on which to construct or deploy nutrient-reduction projects. Nevertheless, the Town is committed to making every reasonable effort to comply with the BMAP and is actively working to catch up by evaluating regulatory, educational, restoration, and partnership-based strategies, including seeking participation from private owners with control of the land within the Town. However, no associated capital expenditure projects have been identified yet for Fiscal Year 2026-2027.